1990 – 1998
- Riverbend site prep
- McBride site prep
- Vulcan sub extension
- Flat Lake 242S site prep
- Red Deer to Joffre (138 KV line – 30 km)
- Balzac Turbo 121S Enmax site prep
- Airdrie Highway #36 sub extension
- Brooks in town sub extension
- Taber 83S sub extension
1999 – 2006
- 1201 Line, providing new access, brushing, burning and reclamation. Trans Alta Utilities
- Black Diamond Sub, removed and replaced insulation gravel. Trans Alta Utilities
- Secondary Highway # 533 Upgrade, hauled and supplied gravel. Municipal District of Ranchlands #66
- 784 Line, provided right of way preparation, clean up and reclamation. Trans Alta Utilities
- 428 Sub (Namaka), provided site prep. Ramco Electric Consulting Ltd.
- Brazeau Steel Line, provided railway tie retention wall for erosion of steel tower. Trans Alta Utilities
- 756 Line, provided access replacement. Trans Alta Utilities
- Magrath Sub extension. Trans Alta Utilities
- 1201 Line Sec. # 4, provided permanent access to tower line. Trans Alta Utilities
- 756 Line Red Deer to Joffre (138 KV Co-Generation), provided access, clean up and reclamation. Trans Alta Utilities
- 500 K Test line, provided Janet tower, footing and salvaging. Trans Alta Utilities
- Namaka Line, provided clean up removal of tree stumps and reclamation. Trans Alta Utilities
- Strathmore Sub station, provided reclamation and re – graveled insulation gravel around the perimeter. Trans Alta Utilities
- Country roads re – gravel, supplied and hauled gravel. Municipal District of Ranchlands #66
- Standard Sub station, provided clean up and reclamation. Utilicorp Networks Canada
- 756 Line, installed concrete low level crossing, clean up storage yard of pole stubs and concrete. TransAlta Utilities
- Ponoka Line, provided clean up of concrete and old poles and built new access. Trans Alta Utilities
- Carsland Fertilizer Plant Sub Station, provided sub extension. Trans Alta Utilities
- Gleichen Sub, re – graveled insulation perimeter gravel, landscape and reclamation. Trans Alta Utilities
- 24S site Prep, installed insulation gravel, landscape and reclamation. Enmax
- Balzac Sub extension. Trans Alta Utilities
- Strathmore 151S, provided substation extension. Trans Alta Utilities
- Enbridge Upgrade, provided 216S Edmonton Sub extension, 299S Kingman Sub extension, 223 Strome sub extension, 377S Hardisty Sub extension, 221S Sunkin Lake Sub extension. Trans Alta Utilities
- 242S Flat Lake, Provided Site prep. Trans Alta Utilities
- Namaka Sub, perimeter reclamation. Trans Alta Utilities
- Beddington Sub, site prep of the top 300mm and built a retention pond. High Time Industries
- Coaldale Sub, provided site prep and access road. SNC Lavalin ATP Inc.
- Pinedale Sub, provided site prep and access road. SNC Lavalin ATP Inc.
- Trans Canada Pipeline Sub Upgrade, provided bank stabilization and upgrade. High Time Industries
- Carvel Sub, provided site prep and access road. SNC Lavalin ATP Inc.
- Enmax Sub #7, provided site prep and access road. Enmax
- Bretona Sub, provided site prep and access road. SNC Lavalin ATP Inc.
- Viscount 92S Sub, provided site prep and access road. SNC Lavalin ATP Inc.
- Flood Restoration. Municipal District of Ranchlands #66
- 906L , provided tower replacement on Sarcee Trail and 17th Ave. SNC Lavalin ATP Inc.
- 42S Sub extension. Site prep. SNC Lavalin ATP Inc.
- Strathmore Sub extension. SNC Lavalin ATP Inc.
- Suffield Sub extension SNC Lavalin ATP Inc.
- Bassano Road Upgrade. SNC Lavalin ATP Inc.
- Enmax Sub Station # 26. Enmax
- Soderglen Wind Farm Sub station. High Time Industries
2007 – 2008
- Keephills Site Prep. BMK Power Ltd.
- Secondary Highway 940, hauled and supplied gravel, MD of Ranchlands No. 66
- #55 Sub, hauled and supplied insulating gravel, High Time Industries Ltd.
- 305S, 538S Fortis Metering Station Site Prep, High Time Industries Ltd.
- Dry Creek Sub Station, Hauled and supplied insulating gravel, BMK Power Ltd.
- Sub Station #26, Clean up, hauled and supplied insulating gravel, Enmax
- Sub Station # 9, 13, 21, 23, 24, 30, 36, 37, 38, 41 & 58 Clean up, hauled and supplied insulating gravel, Enmax
- 820 Line SW Development Clean up, SNC Lavalin ATP Inc.
- Stirling Sub, hauled and supplied insulating gravel, High Time Industries Ltd.
- 138KV Underground repair Downtown Calgary Enmax
- Waupisoo 405S Site Prep, Hightime Industries Ltd.
- Burdett Sub Extension, SNC Lavalin
- Enmax Site Prep #6 Substation, Enmax
2009-2010
- (85+) Fortis AMI Metering Pads throughout Alberta for High Time Industries Ltd.
- Supply and deliver insulating gravel for Substations throughout Alberta.
- Supply, deliver, clean out and spread insulating gravel Enmax Substation #14.
- Supply, deliver insulating gravel for Enmax Substations #5, #38, #2, #21 Substations.
- Right of way construction for Enmax Crossfield Substation for Peterson Land Consulting Ltd.
- Trenching in Lethbridge 370 Substations, Saddlebrook and Burderheim for High Time Industries Ltd.
- Berming and Site Preparation Enmax Substation #47.
- Berming and Site Preparation Enmax Substation #162.
- Substation Site Preparation in Fort Assiniboine for Westwood Electric Ltd.
- Regravel Country Roads – MD of Ranchlands #66.
- Snow Removal Enmax Substations #31, #30, #33.
- Pile Demolition for Enmax Substations #13, #30, #33.
- Structure #155 Access Pad in Lethbridge for SNC Lavalin T & D.
- SW Reclamation Project for SNC Lavalin T & D
2011
- ALPAC ROW – SNC Lavalin T & D
- ALPAC Site preparation – SNC Lavalin T & D
2012
- Edmonton 240 kV Line upgrade for SNC Lavalin T & D
- Leduc 325S line upgrade for SNC Lavalin T & D
- Entwhistle Sub extension/repair/access road/reclaimation for Valard Construction
- Regravel Country Roads – MD of Ranchlands #66
- # 36 Sub Extension for Enmax Power Corporation
- New Road access #26 Sub for Enmax Power Corporation
2013
- Edmonton 240 kV Line upgrade for SNC Lavalin T & D
- Leduc 325S Line upgrade for SNC Lavalin T & D
- Keystone Substation Site Preparation for Valard Construction
- Rimbey Substation 297S Substation Site Preparation for CANA High Voltage Ltd.
- MD or Ranchlands # 66 Regravel project
- Hull Substation Site Preparation (Taber, AB – Current)
2014
- NW Upgrader, SNC Lavalin ATP Inc.
- WATL Right of way Preparation, Reclamation & Fencing, SNC Lavalin ATP Inc.
- Cherhill 338S, Reclamation & Fencing, SNC Lavalin ATP Inc.
- 1043 Line, Right of way Preparation, Reclamation & Fencing, SNC Lavalin ATP Inc.
- Timberland Substation Site Prep, Cana High Voltage
- Echville 534S Substation Extension, Cana High Voltage
- Buck Lake, Reclamation & Fencing, Rising Edge Technologies
- 80L North, 637L, 648L, Right of way Prep and Reclamation, Rokstad Power
- Regravel roads, MD of Ranchlands #66
2015
- RATD 80L North, 80L South, Wolf Creek, Johnson 281S, 637L/648L Rebuild, Right of way Prep and reclamation, Reclamation, SNC Lavalin ATP Inc.
- WATL, Right of way Preparation and Reclamation, SNC Lavalin ATP Inc.
- NW upgrader, Right of way Preparation and Reclamation SNC Lavalin ATP Inc.
- Timberland Substation, Site Preparation, CANA High Voltage
- Johnson 281S, Wolf Creek, Excavation of Ground Cables and Cable Vaults, Cana High Voltage
- Windy Flats, Excavation of Ground Cables and Cable Vaults, Iconic Power Systems
- Regravel roads, MD of Ranchlands #66